Flood Control and Drainage21CK0093

REHABILITATION OF EXISTING DIKE ALONG O'DONNELL RIVER (STA.LUCIA SECTION, RIGHT BANK), CAPAS, TARLAC

REHABILITATION OF EXISTING DIKE ALONG O'DONNELL RIVER (STA.LUCIA SECTION, RIGHT BANK), CAPAS, TARLAC is a DPWH-tracked public work in Tarlac 2nd DEO, Region III. Reported contract value: ₱48,999,342.63. Status: Reported complete (DPWH). Contractor on record: 11-16 CONST. Figures trace to dpwh.

Tarlac 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱11,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structures Along Tarlac River Control Right Dike, Cardona - Ayson Section, Gerona, Tarlac
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Tarlac 2nd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

244 projects · ₱19.8B total · 0 flags

4. Implementation

Contract Amount

₱48,999,342.63

Progress

Reported complete (DPWH)

Start Date

May 4, 2021

Target End

December 14, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.