Buildings and Facilities24PL0067

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (GYM) AT MALAGNAT NATIONAL HIGH SCHOOL, BARANGAY MALAGNAT, PINUKPUK, KALINGA

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (GYM) AT MALAGNAT NATIONAL HIGH SCHOOL, BARANGAY MALAGNAT, PINUKPUK, KALINGA is a DPWH-tracked public work in Lower Kalinga DEO, Cordillera Administrative Region. Reported contract value: ₱3,958,752.76. Status: Past target date (DPWH On-Going). Contractor on record: RIOS CONST SERVICES. Figures trace to dpwh.

Lower Kalinga DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Malagnat / Callagdao / Lay - asan / Mangali Elementary School in Barangay Malagnat, Barangay Bulanao Centro, Barangay Lay - asan and Barangay Mangali, Pinukpuk, Tabuk City, and Tanudan, Kalinga
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Lower Kalinga DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

6 projects · ₱53.3M total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS - MT PROVINCE BDRY-CALANAN-PINUKPUK-ABBUT RD (CALANAN-PINUKPUK SECT) - K0502 + 000 - K0502 + 800

Lower Kalinga DEO, Cordillera Administrative Region

2025₱23.4M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUTURE PROGRAM (BIP) - BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS CONNECTING TO INDIGENOUS PEOPLE (IP) COMMUNITIES - CONSTRUCTION OF ROAD, MABACA-PANGOL, UPPER TANGBAY, AMBITIN- CALLAGD

Lower Kalinga DEO, Cordillera Administrative Region

2025₱8.3M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BIP - INTERJURISDICTIONAL ROADS AND/OR BRIDGES (OR, ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS) - CONSTRUCTION OF BACLAYAM ELEMENTARY SCHOOL ROAD - PUROK EVERLASTING - AYUNGAN - CUDAL - BULNINAN ACCESS

Lower Kalinga DEO, Cordillera Administrative Region

2024₱7.9M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, MALAGNAT/ CALLAGDAO/ LAY-ASAN/ MANGALI ELE

Lower Kalinga DEO, Cordillera Administrative Region

2024₱4.9M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE (UBBOG SAN JUAN) ALONG BALIGAT

Lower Kalinga DEO, Cordillera Administrative Region

2025₱4.8M
Past target date (DPWH On-Going)
View all 6 projects →

4. Implementation

Contract Amount

₱3,958,752.76

Progress

Past target date (DPWH On-Going)

Start Date

July 11, 2024

Target End

March 7, 2025

5. Audit