Buildings and Facilities18KE0017

CONSTRUCTION OF COVERED COURT BARANGAY CABUAN GUINSILIBAN

CONSTRUCTION OF COVERED COURT BARANGAY CABUAN GUINSILIBAN is a DPWH-tracked public work in Camiguin DEO, Region X. Reported contract value: ₱1,886,935.34. Status: Reported complete (DPWH). Contractor on record: GCMG CONST. Figures trace to dpwh.

Camiguin DEO, Region X
Region: Region X

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱1,886,935.34

Progress

Reported complete (DPWH)

Start Date

March 14, 2018

Target End

June 1, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.