Construction of Flood Mitigation Structure21DO0038

Construction of for Slope Protection (Portion) of Pililia River, Sitio Libid, Barangay Hulo, Pililia, Rizal

Construction of for Slope Protection (Portion) of Pililia River, Sitio Libid, Barangay Hulo, Pililia, Rizal is a DPWH-tracked public work in RIZAL, Region IV-A. Reported contract value: ₱8,173,647.31. Status: Reported complete (DPWH). Contractor on record: JCML BUILDERS. Figures trace to sumbong.

RIZAL, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Angono River, Barangay San Isidro, Angono Rizal
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0012598

₱142,000,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0013376

₱5,000,000.00 · FY2021

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱8,173,647.31

Progress

Reported complete (DPWH)

Start Date

December 24, 2021

Target End

July 23, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.