Construction of Flood Mitigation Structure25ED0055

Construction of River Control Structure, Bucayao River, Managpi Section, Calapan City, Oriental Mindoro

Construction of River Control Structure, Bucayao River, Managpi Section, Calapan City, Oriental Mindoro is a DPWH-tracked public work in CITY OF CALAPAN (CAPITAL) (ORIENTAL MINDORO), ORIENTAL MINDORO, Region IV-B. Reported contract value: ₱19,299,949.90. Status: Reported complete (DPWH). Contractor on record: CEFF TRADING & ENGINEERING SERVICES. Figures trace to sumbong.

CITY OF CALAPAN (CAPITAL) (ORIENTAL MINDORO), ORIENTAL MINDORO, Region IV-B
Region: Region IV-B

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Brgy. Lalud, Calapan City, Oriental Mindoro
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-25-0001920

₱5,286,865.00 · FY2025

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-25-0003500

₱2,549,000.00 · FY2025

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-25-0001921

₱487,400.00 · FY2025

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-25-0008147

₱454,655,000.00 · FY2025

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-25-0003501

₱256,000.00 · FY2025

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-25-0019249

₱233,000.00 · FY2025

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-25-0010975

₱29,674.00 · FY2025

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-25-0010872

₱377,278.00 · FY2025

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱19,299,949.90

Progress

Reported complete (DPWH)

Start Date

March 13, 2025

Target End

October 14, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.