GAA 2025 SSP25A00486

BASIC INFRASTRUCTURE PROGRAM (BIP) - CLUSTER V (1. CONSTRUCTION OF ROADS AT BRGY. DOYONG, CALASIAO, PANGASINAN; 2. CONSTRUCTION OF ROADS AT BRGY. MANCUP, CALASIAO, PANGASINAN; 3. CONSTRUCTION OF ROADS AT BRGY.MALABAGO, CALASIAO, PANGASINAN)

BASIC INFRASTRUCTURE PROGRAM (BIP) - CLUSTER V (1. CONSTRUCTION OF ROADS AT BRGY. DOYONG, CALASIAO, PANGASINAN; 2. CONSTRUCTION OF ROADS AT BRGY. MANCUP, CALASIAO, PANGASINAN; 3. CONSTRUCTION OF ROADS AT BRGY.MALABAGO, CALASIAO, PANGASINAN) is a DPWH-tracked public work in Region I, Region I. Reported contract value: ₱28,795,850.57. Status: Past target date (DPWH On-Going). Contractor on record: R T MACANLALAY CONST. Figures trace to dpwh.

Region I, Region I
Region: Region I

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2025 GAA. DBM GAA FY2025

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

13 projects · ₱220.2M total · 0 flags

4. Implementation

Contract Amount

₱28,795,850.57

Progress

Past target date (DPWH On-Going)

Start Date

May 27, 2025

Target End

November 4, 2025

5. Audit