Roads18PB0030

IMPROVEMENT/ CONCRETING OF MAUBBA-CAGLAYAN FARM-TO-MARKET ROAD, BRGY. CAGLAYAN, CONNER, APAYAO

IMPROVEMENT/ CONCRETING OF MAUBBA-CAGLAYAN FARM-TO-MARKET ROAD, BRGY. CAGLAYAN, CONNER, APAYAO is a DPWH-tracked public work in Apayao 1st DEO, Cordillera Administrative Region. Reported contract value: ₱4,923,660.28. Status: Reported complete (DPWH). Contractor on record: BLESSING BUILDERS AND CONST SUPPLY. Figures trace to dpwh.

Apayao 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱38,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Cupis Flood Control, Brgy. Cupis, Conner, Apayao
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-18-0014195

₱1,289,440.00 · FY2018

Released to Southern Philippines Medical Center (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

100 projects · ₱723.5M total · 0 flags

Other projects by this contractor

No sat.

PACKAGE 1: REHABILITATION/RECONSTRUCTION OF RD WITH SLIPS, SLOPE COLLAPSE & LANDSLIDE NAT'L RD, MT. PROVINCE-CALANAN-PINUKPUK-ABBUT RD, A) K0524-460 - K0524+490, B) K0524+460 - K0524+510, C) K0524+520 - K0524+550, D) K0530+600 - K0530+620, E)K0531+790 - K

Lower Kalinga DEO, Cordillera Administrative Region

2018₱44.1M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT: PAVING OF UNPAVED ROADS - TERTIARY ROADS LUBUAGAN - BATONG BUHAY - ABRA BDRY RD K0473 + 738 - K0474 + 690

Upper Kalinga DEO, Cordillera Administrative Region

2021₱36.3M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ABLEG-MOLAYONG-AMDALAO RD

Upper Kalinga DEO, Cordillera Administrative Region

2024₱33.5M
Past target date (DPWH On-Going)
No sat.

ASSET PRESERVATION - REHABILITATION/ RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS, APAYAO-ILOCOS NORTE RD - K0623+020 - K0623+735

Apayao 1st DEO, Cordillera Administrative Region

2021₱28.7M
Reported complete (DPWH)
No sat.

OFF-CARRIAGE IMPROVEMENT INCLUDING DRAINAGE SECONDARY ROADS, ABBUT-CONNER ROADS, K0540+(-375) - K0540+(-255), K0540+(-225) - K0540+(-085), K0540+(-085) - K0541+240, K0541+258 - K0541+534

Apayao 1st DEO, Cordillera Administrative Region

2017₱27.1M
Reported complete (DPWH)
No sat.

REPAIR/REHABILITATION OF ROAD PROJECTS IN APAYAO DAMAGED BY TYPHOON FALCON

Apayao 1st DEO, Cordillera Administrative Region

2019₱25.6M
Reported complete (DPWH)
View all 100 projects →

4. Implementation

Contract Amount

₱4,923,660.28

Progress

Reported complete (DPWH)

Start Date

June 12, 2018

Target End

January 19, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.