Roads21J00041

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ZAMBOANGA CITY BY-PASS ROAD, PATALON (WEST), PACKAGE 5, ZAMBOANGA CITY

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ZAMBOANGA CITY BY-PASS ROAD, PATALON (WEST), PACKAGE 5, ZAMBOANGA CITY is a DPWH-tracked public work in Region IX, Region IX. Reported contract value: ₱84,655,072.47. Status: Past target date (DPWH On-Going). Contractor on record: PRIMETECH CONST AND TRADING. Figures trace to dpwh.

Region IX, Region IX
Region: Region IX

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2021 GAA. DBM GAA FY2021

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱84,655,072.47

Progress

Past target date (DPWH On-Going)

Start Date

March 27, 2021

Target End

October 29, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.