GAA 2024 OO-124GP0023

ROAD WIDENING- CAPIZ- AKLAN ROAD- K0325+781- K0326+100, K0327+380- K0327+594, K0329+648- K0329+746, K0329+798- K0329+889, K0330+375- K0330+475, K0330+722- K0330+887, K0330+894- K0331+003

ROAD WIDENING- CAPIZ- AKLAN ROAD- K0325+781- K0326+100, K0327+380- K0327+594, K0329+648- K0329+746, K0329+798- K0329+889, K0330+375- K0330+475, K0330+722- K0330+887, K0330+894- K0331+003 is a DPWH-tracked public work in Capiz 2nd DEO, Region VI. Reported contract value: ₱57,856,981.63. Status: Past target date (DPWH On-Going). Contractor on record: STEVEN CONST. Figures trace to dpwh.

Capiz 2nd DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

Possible match · score 79%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Barangay VI and VII, Roxas City, Capiz
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Capiz 2nd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

252 projects · ₱7.4B total · 0 flags

Other projects by this contractor

No sat.

REHABILITATION/RECONSTRUCTION AND IMPROVEMENT OF FLOOD CONTROL STRUCTURES ALONG TAGAYTAY RIVER, BRGY. TAGAYTAY-BARIW, CAMALIG, ALBAY, CAMALIG, ALBAY (2ND LEGISLATIVE DISTRICT)

Region V, Region V

2024₱164.9M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2 - PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF LEFT AND RIGHT SIDE UGSONG RIVER FLOOD CONTROL STRUCT

Albay 3rd DEO, Region V

2025₱138.8M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-CONSTRUCTION_IMPROVEMENT OF ACCESS ROADS LEADING TO TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP)-MATNOG-BULAN-MAGALLANES WEST COAST HIGHWAY, SORSOGON PACKAGE I MAGALLANES, SORSOGON

Sorsogon DEO, Region V

2022₱108.2M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-CONSTRUCTION_IMPROVEMENT OF ACCESS ROADS LEADING TO TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP)-MATNOG-BULAN-MAGALLANES WEST COAST HIGHWAY, SORSOGON PACKAGE II, MAGALLANES, SORSOGON

Sorsogon DEO, Region V

2022₱106.1M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS-MATNOG-BULAN-MAGALLANES WEST COAST HIGHWAY, SORSOGON PACKAGE I MAGALLANES, SORSOGON

Sorsogon DEO, Region V

2021₱96.5M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION_IMPROVEMENT OF ACCESS ROADS LEADING TO SEAPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM-KATUPARAN)-ACCESS ROAD LEADING TO SORSOGON CITY PORT, SORSOGON

Sorsogon DEO, Region V

2023₱93.6M
Reported complete (DPWH)
View all 252 projects →

4. Implementation

Contract Amount

₱57,856,981.63

Progress

Past target date (DPWH On-Going)

Start Date

February 19, 2024

Target End

January 17, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.