Roads22GF0079

REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - GUIMBAL-IGBARAS-TUBUNGAN-LEON RD. K0039+518 - K0039+907, K0045+201 - K0045+896

REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - GUIMBAL-IGBARAS-TUBUNGAN-LEON RD. K0039+518 - K0039+907, K0045+201 - K0045+896 is a DPWH-tracked public work in Iloilo 1st DEO, Region VI. Reported contract value: ₱25,233,384.20. Status: Reported complete (DPWH). Contractor on record: A D PENDON CONST. Figures trace to dpwh.

Iloilo 1st DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱6,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of San Joaquin Flood Mitigation Shoreline Protection, Barangay Purok 1, San Joaquin, Iloilo
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Iloilo 1st DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

4. Implementation

Contract Amount

₱25,233,384.20

Progress

Reported complete (DPWH)

Start Date

March 29, 2022

Target End

November 10, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.