Roads24BK0029

BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF SAN BENIGNO ROAD, BARANGAY SAN BENIGNO, AGLIPAY, QUIRINO

BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF SAN BENIGNO ROAD, BARANGAY SAN BENIGNO, AGLIPAY, QUIRINO is a DPWH-tracked public work in Quirino DEO, Region II. Reported contract value: ₱4,947,930.93. Status: Reported complete (DPWH). Contractor on record: JURIS CONST. Figures trace to dpwh.

Quirino DEO, Region II
Region: Region II

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Addalam River Flood Control, Downstream ( Disiluad Section ) , Aglipay, Quirino
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Quirino DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

59 projects · ₱362.8M total · 0 flags

Other projects by this contractor

View all 59 projects →

4. Implementation

Contract Amount

₱4,947,930.93

Progress

Reported complete (DPWH)

Start Date

February 8, 2024

Target End

November 4, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.