Roads20FB0069

CONSTRUCTION OF POBLACION ROAD, MANITO, ALBAY

CONSTRUCTION OF POBLACION ROAD, MANITO, ALBAY is a DPWH-tracked public work in Albay 2nd DEO, Region V. Reported contract value: ₱9,649,624.55. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: DN'D CONST AND DEVELOPMENT. Figures trace to dpwh.

Albay 2nd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bariw-Libod River, Camalig, Albay
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Albay 2nd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

62 projects · ₱1.4B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP)-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE TRAINING AND INSTRUCTION FACILITY/MEETINGS, INCENTIVES, CONFERENCES FOR EDUCATION AND S

Region V, Region V

2024₱147.0M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS-DAANG MAHARLIKA (LZ)-K0534+630.00-K0537+834.90; K0537+850.40-K0538+400.00, DARAGA, ALBAY 2ND LEGISLATIVE DISTRICT

Region V, Region V

2019₱126.3M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF BY-PASS AND DIVERSION ROAD, JCT. NATO-SABANG COASTAL ROAD, NATO SECTION, CAMARINES SUR PACKAGE B, SAGNAY, CAMARINES SUR

Camarines Sur 4th DEO, Region V

2024₱96.5M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/ OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - REHABILITATION OF STA. CRUZ - PINTOR

Albay 3rd DEO, Region V

2025₱93.6M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/ OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - REHABILITATION OF STA. CRUZ - PINTOR

Albay 3rd DEO, Region V

2025₱93.6M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR / STRATEGIC PUBLIC BUILDINGS / FACILITIES - CONSTRUCTION OF FLOOD CONTROL STRUCTURES, BRGY. ALNAY, POLANG

Albay 3rd DEO, Region V

2025₱74.9M
Past target date (DPWH On-Going)
View all 62 projects →

4. Implementation

Contract Amount

₱9,649,624.55

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

February 7, 2020

Target End

April 19, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.