Flood Control and Drainage25I00073

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE AND DRAINAGE SYSTEM ALONG BANGON RIVER, PHASE 3, BARANGAY SAN JOSE, PALO, LEYTE

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE AND DRAINAGE SYSTEM ALONG BANGON RIVER, PHASE 3, BARANGAY SAN JOSE, PALO, LEYTE is a DPWH-tracked public work in Region VIII, Region VIII. Reported contract value: ₱236,151,922.78. Status: Past target date (DPWH On-Going). Contractor on record: EZJONES CONST INC. Figures trace to dpwh.

Region VIII, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2025 GAA. DBM GAA FY2025

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

287 projects · ₱36.2B total · 7 flags

Other projects by this contractor

View all 287 projects →

4. Implementation

Contract Amount

₱236,151,922.78

Progress

Past target date (DPWH On-Going)

Start Date

March 7, 2025

Target End

March 1, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.