Roads24AB0108

REPAIR/REHABILITATION OF DAMAGED PCCP ALONG BATAC-PINILI ROAD K0 483+100 - K0484+000 AND PINILI-NIEVA ERA ROAD K0469+000 - K0470+000 (INTERMITTENT SECTION)

REPAIR/REHABILITATION OF DAMAGED PCCP ALONG BATAC-PINILI ROAD K0 483+100 - K0484+000 AND PINILI-NIEVA ERA ROAD K0469+000 - K0470+000 (INTERMITTENT SECTION) is a DPWH-tracked public work in Ilocos Norte 2nd DEO, Region I. Reported contract value: ₱0.00. Status: Ongoing (DPWH-reported) (For Procurement (DPWH-reported)). Contractor on record: Contractor not linked in this database. Figures trace to dpwh.

Ilocos Norte 2nd DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Pinili - Nueva Era Road, Downstream and Upstream of Sto. Tomas Bridge 1, Pinili, Ilocos Norte
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Ilocos Norte 2nd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱0.00

Progress

For Procurement (DPWH-reported)

Start Date

Data not yet available

Target End

Data not yet available

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.