Buildings and Facilities25AB0019

BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT) BARANGAY SAN PABLO, SAN NICOLAS, ILOCOS NORTE

BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT) BARANGAY SAN PABLO, SAN NICOLAS, ILOCOS NORTE is a DPWH-tracked public work in Ilocos Norte 2nd DEO, Region I. Reported contract value: ₱2,940,245.23. Status: Past target date (DPWH On-Going). Contractor on record: MARTIN DEVELOPMENT CORP. Figures trace to dpwh.

Ilocos Norte 2nd DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱27,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation/Drainage Structure from Barangay San Francisco, Brgy. San Baltazar, Brgy. San Ildefonso, Brgy. San Bartolome, Brgy. San Silvestre and San Juan Bautista, San Nicolas, Ilocos Norte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Ilocos Norte 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

8 projects · ₱142.0M total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF 4STY12CL & 4STY8CL SOLSONA NATIONAL HIGH SCHOOL, SOLSONA, ILOCOS NORTE

Ilocos Norte 2nd DEO, Region I

2024₱61.1M
Past target date (DPWH On-Going)
No sat.

'SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, IMPROVEMENT OF BRIDGE LEADING TO ROAD AT BARANGAY ESCODA, MARCOS, ILOCOS NORTE

Ilocos Norte 2nd DEO, Region I

2025₱28.5M
Past target date (DPWH On-Going)
No sat.

SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD LEADING TO BUGNAY SWIP, BRGY. SAN AGUSTIN, SAN NICOLAS, ILOCOS NORTE

Ilocos Norte 2nd DEO, Region I

2025₱28.1M
Past target date (DPWH On-Going)
No sat.

BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI PURPOSE BUILDING (COVERED COURT), BRGY. DALAYAP, PINILI, ILOCOS NORTE

Ilocos Norte 2nd DEO, Region I

2025₱6.7M
Past target date (DPWH On-Going)
No sat.

BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD FROM SITIO 1 TO SITIO 5, BARANGAY SAN PABLO, SAN NICOLAS, ILOCOS NORTE

Ilocos Norte 2nd DEO, Region I

2025₱4.9M
Past target date (DPWH On-Going)
No sat.

BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY SAN PABLO, SAN NICOLAS, ILOCOS NORTE

Ilocos Norte 2nd DEO, Region I

2025₱4.9M
Past target date (DPWH On-Going)
View all 8 projects →

4. Implementation

Contract Amount

₱2,940,245.23

Progress

Past target date (DPWH On-Going)

Start Date

February 21, 2025

Target End

April 21, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.