Flood Control and Drainage21CL0050

CONSTRUCTION OF SLOPE PROTECTION AT BARANGAY 2B AND PUROK 6, BARANGAY SAN MIGUEL, SAN ANTONIO, ZAMBALES

CONSTRUCTION OF SLOPE PROTECTION AT BARANGAY 2B AND PUROK 6, BARANGAY SAN MIGUEL, SAN ANTONIO, ZAMBALES is a DPWH-tracked public work in Zambales 1st DEO, Region III. Reported contract value: ₱2,881,168.94. Status: Reported complete (DPWH). Contractor on record: LEO-J CONST SERVICES 27248. Figures trace to dpwh.

Zambales 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱3,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of slope protection/flood control at Gabor Dike Phase V, San Felipe, Zambales
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Zambales 1st DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱2,881,168.94

Progress

Reported complete (DPWH)

Start Date

March 8, 2021

Target End

June 5, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.