Roads23MI0059

PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - MAKILALA - ALLAH VALLEY RD - K1635+520 - K1636+796, K1637+035 - K1637+926

PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - MAKILALA - ALLAH VALLEY RD - K1635+520 - K1636+796, K1637+035 - K1637+926 is a DPWH-tracked public work in Cotabato 3rd DEO, Region XII. Reported contract value: ₱76,909,574.48. Status: Reported complete (DPWH). Contractor on record: JARGON CONST. Figures trace to dpwh.

Cotabato 3rd DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱41,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Kabacan River Flood Control Project (Plang to Pulangi River Section-Phase IV), USM, Kabacan, North Cotabato
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Cotabato 3rd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱76,909,574.48

Progress

Reported complete (DPWH)

Start Date

April 4, 2023

Target End

July 27, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.