CONSTRUCTION OF FOUR (4) STOREY TWENTY FOUR (24) CLASSROOM SCHOOL BUILDING, PADRE GARCIA NHS, PADRE GARCIA, BATANGAS

CONSTRUCTION OF FOUR (4) STOREY TWENTY FOUR (24) CLASSROOM SCHOOL BUILDING, PADRE GARCIA NHS, PADRE GARCIA, BATANGAS is a DPWH-tracked public work in Batangas 4th DEO, Region IV-A. Reported contract value: ₱38,708,475.20. Status: Reported complete (DPWH). Contractor on record: ED1SON DEVELOPMENT. Figures trace to dpwh.

Batangas 4th DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱38,708,475.20

Progress

Reported complete (DPWH)

Start Date

September 22, 2016

Target End

July 18, 2017