Flood Control and Drainage18PE0020

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE -CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BAUANG RIVER BASIN SABDANG SECTION, STA. 036+280 - STA. 036+680, SABLAN, BENGUET

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE -CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BAUANG RIVER BASIN SABDANG SECTION, STA. 036+280 - STA. 036+680, SABLAN, BENGUET is a DPWH-tracked public work in Benguet 1st DEO, Cordillera Administrative Region. Reported contract value: ₱13,602,936.34. Status: Reported complete (DPWH). Contractor on record: HGW=3 ENGINEERING. Figures trace to dpwh.

Benguet 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Bauang River Basin, Sabdang Section, Sablan, Benguet
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROX-18-0002448

₱14,611.00 · FY2018

Released to Division of Misamis Oriental (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱13,602,936.34

Progress

Reported complete (DPWH)

Start Date

March 12, 2018

Target End

July 26, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.