Roads19LC0392

CONCRETING OF ROAD, BRGY. KATIPUNAN TO BRGY. CACAO, PANABO CITY, DAVAO DEL NORTE

CONCRETING OF ROAD, BRGY. KATIPUNAN TO BRGY. CACAO, PANABO CITY, DAVAO DEL NORTE is a DPWH-tracked public work in Davao del Norte DEO, Region XI. Reported contract value: ₱3,880,791.48. Status: Reported complete (DPWH). Contractor on record: MICAH CONST. Figures trace to dpwh.

Davao del Norte DEO, Region XI
Region: Region XI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱3,880,791.48

Progress

Reported complete (DPWH)

Start Date

August 1, 2019

Target End

September 5, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.