1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROVI-19-0006583

₱185,647.00 · FY2019

Released to Dumalag Central National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱1,880,500.00

Progress

Reported complete (DPWH)

Start Date

June 4, 2019

Target End

July 11, 2019