Buildings and Facilities25IL0045

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI PURPOSE BUILDINGS / FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING, MANHILO NATIONAL HIGH SCHOOL, MAASIN CITY, SOUTHERN LEYTE

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI PURPOSE BUILDINGS / FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING, MANHILO NATIONAL HIGH SCHOOL, MAASIN CITY, SOUTHERN LEYTE is a DPWH-tracked public work in Southern Leyte 1st DEO, Region VIII. Reported contract value: ₱4,945,119.30. Status: Past target date (DPWH On-Going). Contractor on record: DAV-LEY CONST SERVICES INC FORMERLY:DAV-LEY CONST SERVICES. Figures trace to dpwh.

Southern Leyte 1st DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control/Protection Work of Dam, Tam-is Communal Irrigation System, Maasin City, Southern Leyte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Southern Leyte 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

25IL0045 CONVERGENCE AND SPECIAL SUPPORT PROGRAM –

₱4,945,119.30 · DAV-LEY CONSTRUCTION SERVICES

Contractor

B

48 projects · ₱488.9M total · 2 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF BARANGAY BAGONG SILANG R

Southern Leyte 1st DEO, Region VIII

2025₱29.4M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS / FACILITIES CONSTRUCTION OF ROAD, BARANGAY SAN JOAQUI

Southern Leyte 1st DEO, Region VIII

2022₱29.4M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR / STRATEGIC PUBLIC BUILDINGS / FACILITIES - CONSTRUCTION OF BARANGAY CAGNITUAN R

Southern Leyte 1st DEO, Region VIII

2025₱29.4M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF BOGO FLOOD CONTROL, SITIO GUTOSAN, MAASIN CITY, SOUTHERN LEYTE

Southern Leyte 1st DEO, Region VIII

2021₱21.9M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) -BASIC INFRASTRUCTURE PROGRAM (BIP) -FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES - CONSTRUCTION OF FLOOD CONTROL STRUCTURES, STA. SOFIA, PADRE BURGOS, SOUTHERN LEYTE

Southern Leyte 1st DEO, Region VIII

2023₱19.8M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM - ACCESS ROAD AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR / STRATEGIC PUBLIC BUILDINGS / FACILITIES, CONSTRUCTION OF ROAD, PHASE II, MAMBAJAO-NASAUG-BOGO-SITIO GOTOSAN, MAASIN CITY, SOUTHERN LEYTE

Southern Leyte 1st DEO, Region VIII

2023₱19.8M
Reported complete (DPWH)
View all 48 projects →

4. Implementation

Contract Amount

₱4,945,119.30

Progress

Past target date (DPWH On-Going)

Start Date

June 2, 2025

Target End

November 28, 2025

5. Audit