Construction of Flood Mitigation Structure23DI0051

Construction of River Protection Structure along Maitim Waterways, Brgy. Paciano Rizal, Bay, Laguna

Construction of River Protection Structure along Maitim Waterways, Brgy. Paciano Rizal, Bay, Laguna is a DPWH-tracked public work in BAY (LAGUNA), LAGUNA, Region IV-A. Reported contract value: ₱48,233,455.00. Status: Reported complete (DPWH). Contractor on record: MAR-VEL CONST & SUPPLY. Figures trace to sumbong.

BAY (LAGUNA), LAGUNA, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱60,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control (Slope Protection Structure), Barangay Estrella, San Pedro City, Laguna
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Laguna 2nd District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱48,233,455.00

Progress

Reported complete (DPWH)

Start Date

February 24, 2023

Target End

October 12, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.