Buildings and Facilities19CL0045

CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY CASABAAN, CABANGAN, ZAMBALE

CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY CASABAAN, CABANGAN, ZAMBALE is a DPWH-tracked public work in Zambales 1st DEO, Region III. Reported contract value: ₱3,429,749.99. Status: Reported complete (DPWH). Contractor on record: NEW MASINLOC HENRY'S CONST. Figures trace to dpwh.

Zambales 1st DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱3,429,749.99

Progress

Reported complete (DPWH)

Start Date

July 16, 2019

Target End

October 23, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.