Roads24AI0263

CONCRETING OF BRGY. BALLIGI TO BRGY. POBLACION FMR, BRGY. BALLIGI AND BRGY. POBLACION, LAOAC, PANGASINAN

CONCRETING OF BRGY. BALLIGI TO BRGY. POBLACION FMR, BRGY. BALLIGI AND BRGY. POBLACION, LAOAC, PANGASINAN is a DPWH-tracked public work in Pangasinan 3rd DEO, Region I. Reported contract value: ₱12,281,901.29. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: DMGR BUILDERS. Figures trace to dpwh.

Pangasinan 3rd DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Agno and Allied River, Brgy. Amistad - Poblacion, Tayug, Pangasinan, Phase II
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Pangasinan 3rd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

4. Implementation

Contract Amount

₱12,281,901.29

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

September 6, 2024

Target End

November 22, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.