Roads19IJ0215

(RE-ADVERTISED) CONCRETING OF BRGY.MACATINGOG - BRGY. DAWO FMR (PHASE II), BRGY.MACATINGOG AND BRGY. DAWO, CALBAYOG CITY, SAMAR

(RE-ADVERTISED) CONCRETING OF BRGY.MACATINGOG - BRGY. DAWO FMR (PHASE II), BRGY.MACATINGOG AND BRGY. DAWO, CALBAYOG CITY, SAMAR is a DPWH-tracked public work in Samar 1st DEO, Region VIII. Reported contract value: ₱9,134,100.00. Status: Reported complete (DPWH). Contractor on record: JFR CONST INC FORMERLY:JFR CONST 35890. Figures trace to dpwh.

Samar 1st DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱9,134,100.00

Progress

Reported complete (DPWH)

Start Date

December 20, 2019

Target End

July 9, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.