Flood Control and Drainage24LG0015

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG CAMOGNA RIVER, GOVERNOR GENEROSO, DAVAO ORIENTAL

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG CAMOGNA RIVER, GOVERNOR GENEROSO, DAVAO ORIENTAL is a DPWH-tracked public work in Davao Oriental 2nd DEO, Region XI. Reported contract value: ₱19,210,550.91. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: RAKKI CORP 43053. Figures trace to dpwh.

Davao Oriental 2nd DEO, Region XI
Region: Region XI

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱48,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Magdug Creek, Governor Generoso, Davao Oriental
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Davao Oriental 2nd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

4. Implementation

Contract Amount

₱19,210,550.91

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

April 12, 2024

Target End

December 3, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.