Buildings and Facilities16PL0128

CONSTRUCTION OF BULO BHS

CONSTRUCTION OF BULO BHS is a DPWH-tracked public work in Lower Kalinga DEO, Cordillera Administrative Region. Reported contract value: ₱1,379,148.72. Status: Reported complete (DPWH). Contractor on record: O U A CONST. Figures trace to dpwh.

Lower Kalinga DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXII-16-0018250

₱291,777.00 · FY2016

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱1,379,148.72

Progress

Reported complete (DPWH)

Start Date

January 10, 2017

Target End

April 9, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.