Flood Control and Drainage18OE0060

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAITENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS BANK IMPROVEMENT (STEEL SHEET PILE) ESTERO DE SAN MIGUEL STA. 1+963.20 TO STA.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/MAITENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS BANK IMPROVEMENT (STEEL SHEET PILE) ESTERO DE SAN MIGUEL STA. 1+963.20 TO STA. is a DPWH-tracked public work in North Manila DEO, National Capital Region. Reported contract value: ₱27,911,225.89. Status: Reported complete (DPWH). Contractor on record: STO CRISTO CONST. Figures trace to dpwh.

North Manila DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

490 projects · ₱18.9B total · 0 flags

Other projects by this contractor

View all 490 projects →

4. Implementation

Contract Amount

₱27,911,225.89

Progress

Reported complete (DPWH)

Start Date

February 14, 2018

Target End

May 14, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.