Roads16G00070

CONST./IMPVT. OF CONCORDIA - ORACON - BOTCONAWAY ROAD, NUEVA VALENCIA, GUIMARAS, STA. 4+169 - STA. 7

CONST./IMPVT. OF CONCORDIA - ORACON - BOTCONAWAY ROAD, NUEVA VALENCIA, GUIMARAS, STA. 4+169 - STA. 7 is a DPWH-tracked public work in Region VI, Region VI. Reported contract value: ₱75,437,576.77. Status: Reported complete (DPWH). Contractor on record: J E TICO CONST CO INC FORMERLY: JET CO. Figures trace to dpwh.

Region VI, Region VI
Region: Region VI

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱75,437,576.77

Progress

Reported complete (DPWH)

Start Date

June 12, 2016

Target End

February 12, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.