Roads18DG0047

ORGANIZATIONAL OUTCOME 1: ROAD WIDENING-TERTIARY ROADS-INDANG-ALFONSO VIA LUKSUHIN RD. K0057+000 - K

ORGANIZATIONAL OUTCOME 1: ROAD WIDENING-TERTIARY ROADS-INDANG-ALFONSO VIA LUKSUHIN RD. K0057+000 - K is a DPWH-tracked public work in Cavite 2nd DEO, Region IV-A. Reported contract value: ₱21,472,040.41. Status: Reported complete (DPWH). Contractor on record: BAQPRINCE CONST AND TRADING CORP. Figures trace to dpwh.

Cavite 2nd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Revetment along Cañas River, Brgy. Pinagtipunan Section,Phase 2, Gen. Trias, Cavite
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Agency-level releases for FY2018, not tied to this contract

Cavite 2nd DEO · SARO 1,489 (₱126,676,811,675.00) · NCA 1,617 (₱426,584,627,343.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

185 projects · ₱6.3B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAMBASIC INFRASTRUCTURE PROGRAM (BIP)BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICESCONSTRUCTION (COMPLETION) OF ROSARIO GYMNASIUM, ROSARIO, CAVITE

Cavite 1st DEO, Region IV-A

2024₱147.1M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF REVETMENT ALONG CAÑAS RIVER, GENERAL TRIAS, CAVITE, PHASE 3

Region IV-A, Region IV-A

2023₱99.6M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEMNETWORK DEVELOPMENT PROGRAMCONSTRUCTION OF BY-PASS AND DIVERSION ROADSMALABON GRANDE- SAN JUAN - MULAWIN DIVERSION ROAD, LAVANYA SECTION, BRGY. SAN JUAN II, GEN. TRIAS CITY, CAV

Cavite 1st DEO, Region IV-A

2023₱96.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEMNETWORK DEVELOPMENT PROGRAMCONSTRUCTION OF BY-PASS AND DIVERSION ROADSMALABON GRANDE- SAN JUAN - MULAWIN DIVERSION ROAD, MULAWIN SECTION, SEGMENT 3, TANZA, CAVITE

Cavite 1st DEO, Region IV-A

2022₱96.5M
Reported complete (DPWH)

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS FLOOD MANAGEMENT PROGRAM CONST./REHAB. OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS CONST. OF REVETMENT ALONG IMUS RIVER,BRGY.BINAKAYAN, PHASE II

Cavite 1st DEO, Region IV-A

2023₱96.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEMNETWORK DEVELOPMENT PROGRAMCONSTRUCTION OF BY-PASS AND DIVERSION ROADSMALABON GRANDE- SAN JUAN - MULAWIN DIVERSION ROAD, MULAWIN SECTION, SEGMENT 4, TANZA, CAVITE

Cavite 1st DEO, Region IV-A

2022₱96.5M
Reported complete (DPWH)
View all 185 projects →

4. Implementation

Contract Amount

₱21,472,040.41

Progress

Reported complete (DPWH)

Start Date

February 6, 2018

Target End

September 8, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.