Roads22HH0061

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND / OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR / STRATEGIC PUBLIC BUILDINGS / FACILITIES - CONSTRUCTION OF ROAD AT BARANGAY MABINI, CEBU CITY

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND / OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR / STRATEGIC PUBLIC BUILDINGS / FACILITIES - CONSTRUCTION OF ROAD AT BARANGAY MABINI, CEBU CITY is a DPWH-tracked public work in Cebu City DEO, Region VII. Reported contract value: ₱4,938,685.00. Status: Reported complete (DPWH). Contractor on record: RIKDA CONST. Figures trace to dpwh.

Cebu City DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Lahug River, Cebu City
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Cebu City DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

31 projects · ₱74.7M total · 0 flags

Other projects by this contractor

No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT BRGY. TISA, CEBU CITY

Cebu City DEO, Region VII

2020₱6.1M
Reported complete (DPWH)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT BRGY. KINASANG-AN, CEBU CITY

Cebu City DEO, Region VII

2020₱4.9M
Reported complete (DPWH)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL MITIGATION STRUCTURES AT BRGY. KALUNASAN, CEBU CITY

Cebu City DEO, Region VII

2019₱4.3M
Reported complete (DPWH)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL MITIGATION STRUCTURES AT BRGY. BUHISAN, CEBU CITY

Cebu City DEO, Region VII

2019₱4.3M
Reported complete (DPWH)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL MITIGATION STRUCTURES AT BRGY. QUIOT, CEBU CITY

Cebu City DEO, Region VII

2019₱4.2M
Reported complete (DPWH)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL MITIGATION STRUCTURES AT BRGY. BASAK PARDO, CEBU CITY

Cebu City DEO, Region VII

2019₱4.2M
Reported complete (DPWH)
View all 31 projects →

4. Implementation

Contract Amount

₱4,938,685.00

Progress

Reported complete (DPWH)

Start Date

March 24, 2022

Target End

July 6, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.