Buildings and Facilities16OF0042

CONSTRUCTION OF MPB @ SAN PEDRO 1, BRGY. TANDANG SORA, Q.C.

CONSTRUCTION OF MPB @ SAN PEDRO 1, BRGY. TANDANG SORA, Q.C. is a DPWH-tracked public work in Quezon City 1st DEO, National Capital Region. Reported contract value: ₱5,500,405.76. Status: Reported complete (DPWH). Contractor on record: GREENWALL CONST. Figures trace to dpwh.

Quezon City 1st DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structures and Tributaries at Brgy. Payatas, (Phase 2) District II, Quezon City
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-16-0004539

₱560,000.00 · FY2016

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱5,500,405.76

Progress

Reported complete (DPWH)

Start Date

March 28, 2016

Target End

August 24, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.