Buildings and Facilities23FL0069

CONST. OF SECONDARY CLASSROOMS UNDER THE DEPED'S CY 2023 BASIC EDUC'L. FACILITIES FUND - BATCH 1 (CL

CONST. OF SECONDARY CLASSROOMS UNDER THE DEPED'S CY 2023 BASIC EDUC'L. FACILITIES FUND - BATCH 1 (CL is a DPWH-tracked public work in Sorsogon 2nd DEO, Region V. Reported contract value: ₱89,591,802.13. Status: Past target date (DPWH On-Going). Contractor on record: KYLA CONST SUPPLY. Figures trace to dpwh.

Sorsogon 2nd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Purok 2 & 3, Barangay Lajong, Juban, Sorsogon
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Sorsogon 2nd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱89,591,802.13

Progress

Past target date (DPWH On-Going)

Start Date

September 11, 2023

Target End

August 18, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.