Roads25CD0138

REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS STA MARIA NORZAGARAY RD K0041+000 - K0041+1051, K0042+833 - K0042+1004

REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS STA MARIA NORZAGARAY RD K0041+000 - K0041+1051, K0042+833 - K0042+1004 is a DPWH-tracked public work in Bulacan 2nd DEO, Region III. Reported contract value: ₱52,128,124.22. Status: Past target date (DPWH On-Going). Contractor on record: 729 CONST INC FORMERLY 722 CONST INC 21923. Figures trace to dpwh.

Bulacan 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bocaue-Santa Maria River and its tributaries (Tabon Creek), Sta. 04 + 830 - Sta. 04 + 900, Abangan Norte, Marilao, Bulacan
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Bulacan 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 21923

207 projects · ₱6.0B total · 0 flags

Other projects by this contractor

No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - SIPAG - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES / FACILITIES - CONSTRUCTION OF REVETMENT AT MALANGAAN SECTION (SEGMENT A), DONA REMEDIOS TRINIDAD, BULACAN

Region III, Region III

2024₱96.5M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SAN JOSE RIVER, STA. 08+320 STA. 08+620 (PARADA - SAN VICENTE SECTION), SANTA MARIA, BULACAN

Bulacan 2nd DEO, Region III

2025₱96.5M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MEYCAUYAN RIVER AND ITS TRIBUTIARIES, STA 04+000 STA 04+300 (LIPUTAN CONSTANTINO SECTION, RIGHT SIDE), MEYCAUAYAN, BULACAN

Bulacan 2nd DEO, Region III

2024₱96.2M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRA. PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-CONST. OF RIVERBANK PROTECTION STRUCTURE ALONG BALAONG RIVER (SITIO BROWN BRIDGE UPSTREAM), PACKAGE 3, SAN MIGUEL, BULACAN

Bulacan 3rd DEO, Region III

2025₱95.1M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRA. PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES-CONST. OF RIVERBANK PROTECTION STRUCTURE ALONG BALAONG RIVER (SITIO BROWN BRIDGE UPSTREAM), PACKAGE 4, SAN MIGUEL, BULACAN

Bulacan 3rd DEO, Region III

2025₱95.1M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - SIPAG - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES / FACILITIES - CONSTRUCTION OF REVETMENT AT MALANGAAN SECTION (SEGMENT B), DONA REMEDIOS TRINIDAD, BULACAN

Region III, Region III

2024₱95.1M
Past target date (DPWH On-Going)
View all 207 projects →

4. Implementation

Contract Amount

₱52,128,124.22

Progress

Past target date (DPWH On-Going)

Start Date

March 21, 2025

Target End

November 13, 2025

5. Audit