Buildings and Facilities24G00105

COMPLETION/EQUIPPING OF SUPER HEALTH CENTERS - SAN JOAQUIN SUPER HEALTH CENTER, ILOILO

COMPLETION/EQUIPPING OF SUPER HEALTH CENTERS - SAN JOAQUIN SUPER HEALTH CENTER, ILOILO is a DPWH-tracked public work in Region VI, Region VI. Reported contract value: ₱5,949,700.11. Status: Past target date (DPWH On-Going). Contractor on record: A D PENDON CONST. Figures trace to dpwh.

Region VI, Region VI
Region: Region VI

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱5,949,700.11

Progress

Past target date (DPWH On-Going)

Start Date

October 10, 2024

Target End

March 10, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.