Flood Control and Drainage18CC0067

CONSTRUCTION/REHABILITATION OF FLOOD CONTROL STRUCTURES ALONG ANGAT RIVER AT TIBAG, BALIUAG, BULACAN

CONSTRUCTION/REHABILITATION OF FLOOD CONTROL STRUCTURES ALONG ANGAT RIVER AT TIBAG, BALIUAG, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱9,286,616.46. Status: Reported complete (DPWH). Contractor on record: STAR WILLIAM CONST. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction /Rehabilitation of Flood Control Structures along Angat River at Tibag, Baliwag, Bulacan
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROV-18-0010470

₱28,000.00 · FY2018

Released to Abuyog National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱9,286,616.46

Progress

Reported complete (DPWH)

Start Date

March 1, 2018

Target End

June 7, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.