Bridges21DD0267

LOCAL PROGRAM, LOCAL INFRASTRUCTURE PROGRAM, LOCAL ROADS AND BRIDGES, LOCAL BRIDGES, COMPLETION OF BRIDGE AT BRGY. ANTIPOLO DEL SUR, LIPA CITY, BATANGAS

LOCAL PROGRAM, LOCAL INFRASTRUCTURE PROGRAM, LOCAL ROADS AND BRIDGES, LOCAL BRIDGES, COMPLETION OF BRIDGE AT BRGY. ANTIPOLO DEL SUR, LIPA CITY, BATANGAS is a DPWH-tracked public work in Batangas 4th DEO, Region IV-A. Reported contract value: ₱14,404,351.50. Status: Reported complete (DPWH). Contractor on record: N D M SANCHEZ BUILDERS. Figures trace to dpwh.

Batangas 4th DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control, Brgy. Cuta, Batangas City, Province of Batangas
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Batangas 4th DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

188 projects · ₱4.0B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING, ROSARIO, BATANGAS

Region IV-A, Region IV-A

2025₱194.1M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. CASTILLO, PADRE GARCIA, BATANGAS

Batangas 4th DEO, Region IV-A

2024₱115.2M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES, IMPROVEMENT OF BAUAN - MABINI CIRCUMFERENTIAL ROAD, BARANGAY SAN JUAN, MAINAGA SECTION, MABI

Batangas 2nd DEO, Region IV-A

2025₱114.6M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. SAN SEBASTIAN, MATAAS NA KAHOY, BATANGAS

Batangas 3rd DEO, Region IV-A

2023₱99.0M
Past target date (DPWH On-Going)
No sat.

CSSP - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI PURPOSE BUILDING (PAMANTASAN NG LUNGSOD NG SAN PABLO), BRGY SAN JOSE, SAN PABLO CITY, LAGUNA

Laguna 3rd DEO, Region IV-A

2025₱96.5M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (PUBLIC MARKET), ROSARIO, BATANGAS, PHASE 2

Batangas 4th DEO, Region IV-A

2023₱93.6M
Reported complete (DPWH)
View all 188 projects →

4. Implementation

Contract Amount

₱14,404,351.50

Progress

Reported complete (DPWH)

Start Date

October 20, 2021

Target End

March 8, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.