Bridges15IF0147

RETROFITTING/STRENGTHENING OF PERMANENT BRIDGE,KINABAYAN 2(B00214LT)...,ALONG PALOMPON-ISABEL-MERIDA

RETROFITTING/STRENGTHENING OF PERMANENT BRIDGE,KINABAYAN 2(B00214LT)...,ALONG PALOMPON-ISABEL-MERIDA is a DPWH-tracked public work in Leyte 4th DEO, Region VIII. Reported contract value: ₱8,373,038.03. Status: Reported complete (DPWH). Contractor on record: RJIR ENT CORP. Figures trace to dpwh.

Leyte 4th DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 79%

UACS
18001
Amount
₱36,100,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Mahayahay Flood Control along Ormoc - Baybay So. Leyte Boundary Road, Brgy. Mahayahay, Albuera, Leyte
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-D-16-0026520

₱4,691,271.00 · FY2016

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

692 projects · ₱17.7B total · 35 flags

Other projects by this contractor

View all 692 projects →

4. Implementation

Contract Amount

₱8,373,038.03

Progress

Reported complete (DPWH)

Start Date

January 24, 2016

Target End

May 22, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.