Flood Control and Drainage23AF0203

CONST/REHAB OF FLOOD MITIGATION FACILITIES W/IN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONST. OF FLOOD CONTROL STRUC. ALONG ARINGAY RIVER BASIN, BRGY. SAN SIMON WEST, ARINGAY, LA UNION

CONST/REHAB OF FLOOD MITIGATION FACILITIES W/IN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONST. OF FLOOD CONTROL STRUC. ALONG ARINGAY RIVER BASIN, BRGY. SAN SIMON WEST, ARINGAY, LA UNION is a DPWH-tracked public work in La Union 2nd DEO, Region I. Reported contract value: ₱77,183,818.88. Status: Reported complete (DPWH). Contractor on record: SILVERWOLVES CONST CORP 48466. Figures trace to dpwh.

La Union 2nd DEO, Region I
Region: Region I

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Aringay River Basin, Barangay Ambalite, Pugo, La Union
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

La Union 2nd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 48466

150 projects · ₱16.7B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF REVETMENT AND OTHER IMPROVEMENTS ALONG BALUCTOT RIVER, EAST SIDE, BRGY. SALAWAG, DASMARIÑAS, CAVITE

Region IV-A, Region IV-A

2024₱241.4M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF REVETMENT AND OTHER IMPROVEMENTS ALONG BALUCTOT RIVER, EAST SIDE, BRGY. PALIPARAN III, DASMARIÑAS, CAVITE (PHASE I)

Region IV-A, Region IV-A

2024₱241.4M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - SECONDARY ROADS - BENGUET NUEVA VIZCAYA RD, K0283+475 - K0283+575

Cordillera Administrative Region, Cordillera Administrative Region

2023₱241.3M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - SECONDARY ROADS - BENGUET NUEVA VIZCAYA RD, K0283+368 - K0283+475

Cordillera Administrative Region, Cordillera Administrative Region

2023₱241.3M
Reported complete (DPWH)
No sat.

SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239, INSTALLATION OF ROAD SAFETY DEVICES ALONG BAUANG-BAGUIO CITY ROAD, K0261+100 - K0261+300, K0262+300 - K0262+400, K0262+900 - K0263+100, K0263+500 - K0263+900, K0269+600 - K0269+750,

Region I, Region I

2023₱241.2M
Reported complete (DPWH)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG PAGBAHAN RIVER, PHASE 1, BRGY. SAN VICENTE, SANTA CRUZ, OC

Region IV-B, Region IV-B

2024₱241.2M
Reported complete (DPWH)
View all 150 projects →

4. Implementation

Contract Amount

₱77,183,818.88

Progress

Reported complete (DPWH)

Start Date

February 22, 2024

Target End

October 22, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.