Flood Control and Drainage24J00105

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES / FACILITIES - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BARANGAY AYALA, ZAMBOANGA CITY

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES / FACILITIES - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BARANGAY AYALA, ZAMBOANGA CITY is a DPWH-tracked public work in Region IX, Region IX. Reported contract value: ₱96,494,022.80. Status: Past target date (DPWH On-Going). Contractor on record: RCDG CONST CORP 5063. Figures trace to dpwh.

Region IX, Region IX
Region: Region IX

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 5063

265 projects · ₱14.8B total · 0 flags

Other projects by this contractor

View all 265 projects →

4. Implementation

Contract Amount

₱96,494,022.80

Progress

Past target date (DPWH On-Going)

Start Date

March 8, 2024

Target End

January 31, 2025

5. Audit