Water Provision and Storage19FJ0044

CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTOR SYSTEM - RAIN WATER COLLECTORS IN PUBLIC FACILITIES - (18 UNITS)

CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTOR SYSTEM - RAIN WATER COLLECTORS IN PUBLIC FACILITIES - (18 UNITS) is a DPWH-tracked public work in Masbate 3rd DEO, Region V. Reported contract value: ₱3,677,728.86. Status: Reported complete (DPWH). Contractor on record: BRYNE CONST AND SUPPLY 40918. Figures trace to dpwh.

Masbate 3rd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱3,677,728.86

Progress

Reported complete (DPWH)

Start Date

October 31, 2019

Target End

February 27, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.