Rehabilitation / Major Repair of Flood Control Structure21HD0054

Rehabilitation of Flood Control along Balidbid River, Santa Fe, Cebu

Rehabilitation of Flood Control along Balidbid River, Santa Fe, Cebu is a DPWH-tracked public work in CEBU, Region VII. Reported contract value: ₱88,550,330.00. Status: Reported complete (DPWH). Contractor on record: WTG CONST & DEVELOPMENT CORP / ROVILLA CONST. Figures trace to sumbong.

CEBU, Region VII
Region: Region VII

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱7,700,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Cotcot River, Liloan, Cebu
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0008587

₱106,950,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0014120

₱85,000,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0007565

₱80,000,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0007530

₱132,205,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0008984

₱40,000,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0013828

₱3,400,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0007330

₱50,000,000.00 · FY2021

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱88,550,330.00

Progress

Reported complete (DPWH)

Start Date

December 31, 2021

Target End

September 5, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.