Buildings and Facilities19CC0283

CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL) BRGY. GATBUCA, CALUMPIT, BULACAN

CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL) BRGY. GATBUCA, CALUMPIT, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱1,920,635.42. Status: Reported complete (DPWH). Contractor on record: M G FRANCISCO CONST 29831. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱1,920,635.42

Progress

Reported complete (DPWH)

Start Date

November 4, 2019

Target End

January 12, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.