Buildings and Facilities19FA0047

CLUSTER 25-CONSTRUCTION OF MULTI-PURPOSE BUILDING(COVERED COURT/EVACUATION CENTER) AT STO. DOMINGO, TIWI AND TABACO CITY; AND REHAB. OF STO. DOMINGO PUBLIC MARKET (PHASE I), STO. DOMINGO, ALBAY

CLUSTER 25-CONSTRUCTION OF MULTI-PURPOSE BUILDING(COVERED COURT/EVACUATION CENTER) AT STO. DOMINGO, TIWI AND TABACO CITY; AND REHAB. OF STO. DOMINGO PUBLIC MARKET (PHASE I), STO. DOMINGO, ALBAY is a DPWH-tracked public work in Albay 1st DEO, Region V. Reported contract value: ₱48,015,000.00. Status: Reported complete (DPWH). Contractor on record: 3RB CONST. Figures trace to dpwh.

Albay 1st DEO, Region V
Region: Region V

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱48,015,000.00

Progress

Reported complete (DPWH)

Start Date

July 18, 2019

Target End

August 26, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.