Flood Control and Drainage18CC0109

CONSTRUCTION OF FLOOD CONTROL TABANG, GUIGUINTO, BULACAN

CONSTRUCTION OF FLOOD CONTROL TABANG, GUIGUINTO, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱1,862,749.95. Status: Reported complete (DPWH). Contractor on record: M G FRANCISCO CONST 29831. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱1,862,749.95

Progress

Reported complete (DPWH)

Start Date

March 20, 2018

Target End

May 18, 2018

5. Audit