Roads23II0061

CONCRETING OF SITIO KANKINAWAY TO SITIO LAOANGAN TO SITIO ROMBANG, BRGY. POBLACION 7, TO SITIO ILONG BUKID, BRGY. CABABTOAN FMR, BRGY. POBLACION 7 AND BRGY. CABABTOAN, PAMBUJAN, NORTHERN SAMAR

CONCRETING OF SITIO KANKINAWAY TO SITIO LAOANGAN TO SITIO ROMBANG, BRGY. POBLACION 7, TO SITIO ILONG BUKID, BRGY. CABABTOAN FMR, BRGY. POBLACION 7 AND BRGY. CABABTOAN, PAMBUJAN, NORTHERN SAMAR is a DPWH-tracked public work in Northern Samar 2nd DEO, Region VIII. Reported contract value: ₱14,923,375.80. Status: Reported complete (DPWH). Contractor on record: EFC DEVELOPMENT CORP. Figures trace to dpwh.

Northern Samar 2nd DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Concreting of Flood Control Carriageway in Barangay Cagamutan, Gamay, Northern Samar
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Northern Samar 2nd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱14,923,375.80

Progress

Reported complete (DPWH)

Start Date

August 4, 2023

Target End

January 30, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.