Flood Control and Drainage18IF0005

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, AHAG, ORMOC CITY, LEYTE

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, AHAG, ORMOC CITY, LEYTE is a DPWH-tracked public work in Leyte 4th DEO, Region VIII. Reported contract value: ₱24,438,604.62. Status: Reported complete (DPWH). Contractor on record: RJIR ENT CORP. Figures trace to dpwh.

Leyte 4th DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

692 projects · ₱17.7B total · 0 flags

Other projects by this contractor

View all 692 projects →

4. Implementation

Contract Amount

₱24,438,604.62

Progress

Reported complete (DPWH)

Start Date

February 13, 2018

Target End

August 26, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.