Roads20HB0157

LOCAL PROGRAM - LOCAL INFRASTRUCTURE PROGRAM - LOCAL ROADS AND BRIDGES - LOCAL ROADS CONCRETING OF ROADS AT BRGY. IPIL, JAGNA, BOHOL STA. 0+000.00 - STA. 0+314.00

LOCAL PROGRAM - LOCAL INFRASTRUCTURE PROGRAM - LOCAL ROADS AND BRIDGES - LOCAL ROADS CONCRETING OF ROADS AT BRGY. IPIL, JAGNA, BOHOL STA. 0+000.00 - STA. 0+314.00 is a DPWH-tracked public work in Bohol 3rd DEO, Region VII. Reported contract value: ₱4,703,433.98. Status: Reported complete (DPWH). Contractor on record: ALOJA BUILDERS AND REALTY. Figures trace to dpwh.

Bohol 3rd DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

172 projects · ₱1.1B total · 0 flags

Other projects by this contractor

No sat.

LOCAL PROGRAM - LOCAL INFRASTRUCTURE PROGRAM - LOCAL ROADS AND BRIDGES - LOCAL ROADS - CONCRETING OF ROADS AT SITIO CANTUGOP, NAPO TO BRGY. PUTLONGCAM, ALICIA, BOHOL ST. 0+000.00 - STA.3+202.90 WITH EXCEPTION - SECTION 1; STA. 2+065.00 - STA. 2+365 - SECT

Bohol 3rd DEO, Region VII

2020₱49.5M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM- BASIC INFRASTRUCTURE PROGRAM (BIP) ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION (CONCRETING) OF ROAD AT BRGY. WEST CANAYAON TO BRGY. CAL

Bohol 3rd DEO, Region VII

2023₱39.6M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF BRGY. BINLOD BARANGAY ROAD, ARGAO, CEBU

Cebu 2nd DEO, Region VII

2025₱39.5M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM BASIC INFRASTRUCTURE PROGRAM BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES CONSTRUCTION (CONCRETING) OF ROAD AT BARANGAY BUGANG SUR TO BARANGAY C

Bohol 3rd DEO, Region VII

2023₱34.6M
Reported complete (DPWH)
No sat.

CONVERGENCE & SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROADS, VALENCIA, BOHOL, SEC. 1: STA. 0+000.00 - STA

Bohol 3rd DEO, Region VII

2024₱34.6M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM - REHAB./RECONST. OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDES - SECONDARY ROADS, TAGB. EAST ROAD (TAGB.-JAGNA), JAGNA, BOHOL K0193+620.00 - K0193+6

Bohol 3rd DEO, Region VII

2021₱28.1M
Reported complete (DPWH)
View all 172 projects →

4. Implementation

Contract Amount

₱4,703,433.98

Progress

Reported complete (DPWH)

Start Date

September 28, 2020

Target End

December 16, 2020

5. Audit