GAA 2025 SSP25CN0136

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY DIBUT, SAN LUIS, AURORA

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY DIBUT, SAN LUIS, AURORA is a DPWH-tracked public work in Aurora DEO, Region III. Reported contract value: ₱4,856,805.48. Status: Past target date (DPWH On-Going). Contractor on record: RADIANCE TRADERS. Figures trace to dpwh.

Aurora DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱4,856,805.48

Progress

Past target date (DPWH On-Going)

Start Date

May 23, 2025

Target End

September 19, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.